Professional Documents
Culture Documents
Network Models
Network Models
MODELS
DR. LANI D. DEADA, LPT
Network Models
Introduction to network models (e.g., PERT, CPM)
Critical Path Method (CPM)
Program Evaluation and Review Technique (PERT)
Resource leveling and project scheduling
Network Models
Learning Objectives:
• Understand the basics of network models used in
project management.
• Learn how to apply the Critical Path Method (CPM)
and Program Evaluation and Review Technique
(PERT).
• Understand resource leveling and project scheduling
techniques.
Introduction to Network Models
• Network Models: Tools used to plan,
schedule, and control complex projects by
mapping out the sequence of tasks and their
dependencies.
Introduction to Network Models
Critical Path Method (CPM)
• Objective: To identify the longest path of tasks through a project, which determines the
shortest possible project duration.
Steps in CPM:
1. List all tasks: Identify every task required to complete the project.
2. Define dependencies: Determine which tasks depend on the completion of others.
3. Draw the network diagram: Use nodes for tasks and arrows for dependencies.
4. Estimate task durations: Provide a single time estimate for each task.
5. Calculate early and late start/finish times: Determine the earliest and latest times
each task can start and finish without delaying the project.
6. Identify the critical path: The longest path through the network diagram with the least
slack.
• Critical Path: Tasks on this path have zero slack time, meaning any delay in these tasks
will delay the project.
CPM and PERT ACTIVITY
• Objective: Enhance understanding and application of CPM and PERT while
fostering teamwork and communication.
• Instructions:
1. Task Brainstorming: Ask each team to brainstorm and list all the tasks required
to complete their project. Here's the shuffled list:
1. Plan itinerary
2. Confirm attendance
3. Book accommodations
4. Arrange catering
5. Prepare event materials
6. Set up AV equipment
7. Select location
8. Send invitations
9. Arrange transportation
10.Organize team-building activities
CPM and PERT ACTIVITY
2. Task Dependencies: Teams should identify
dependencies and sequence the tasks accordingly,
similar to the example provided.
3.Task Estimation: Each team should estimate the
time required for each task using three estimates:
optimistic (O), most likely (M), and pessimistic (P).
4. PERT Calculations: Teams calculate the expected
time for each task using the PERT formula:
CPM and PERT ACTIVITY
5. Critical Path Identification: Each team determines
the critical path for their project using the estimated
times.
6. Presentation: Have each team present their project
plan, focusing on the critical path and how PERT
estimates influenced their planning.
Introduction to Network Models
Types:
• CPM (Critical Path Method): Focuses on identifying
the longest path of dependent tasks and calculating
the minimum project duration.
• PERT (Program Evaluation and Review
Technique): Used for planning and controlling
projects with uncertain task durations by estimating
the time required for project tasks.
Introduction to Network Models
Purpose and Benefits of Network Models
1.Planning:
• Network models help in breaking down a project into smaller, manageable
tasks, identifying the sequence of these tasks, and determining their
dependencies. This facilitates detailed project planning.
2.Scheduling:
• By mapping out task dependencies, network models assist in creating
realistic project schedules. They help identify critical tasks that directly
affect the project completion date and tasks with flexibility in their timing.
3.Controlling:
• Network models enable continuous monitoring and control of project
progress. Project managers can track the completion of tasks, identify
delays, and take corrective actions to keep the project on track.
Introduction to Network Models
Key Components of Network Models
1.Tasks (or Activities):
1. These are the individual units of work that need to be completed in a project.
Each task has a defined start and end point.
2.Dependencies:
1. These show the relationships between tasks. They indicate which tasks must
be completed before others can start.
3.Nodes:
1. In network diagrams, nodes represent tasks. They can be visualized as
circles or boxes.
4.Arrows (or Arcs):
1. Arrows connect the nodes and represent the dependencies between tasks.
They show the direction and sequence of the tasks.
Example of Key Components of Network Models
• Example Scenario: Organizing a Conference
Key Components:
• Tasks (or Activities): These are the individual units of work that need to be completed. In our example, the tasks could
include:
1. T1: Book venue
2. T2: Invite speakers
3. T3: Design marketing materials
4. T4: Promote the conference
5. T5: Register participants
6. T6: Arrange catering
7. T7: Set up the venue
8. T8: Host the conference
Each task has a defined start and end point. For instance, "Book venue" (T1) starts when the search for venues begins and
ends when the booking is confirmed
Example of Key Components of Network Models
• Dependencies: Dependencies show the relationships between
tasks, indicating which tasks must be completed before others can
start.
For the conference:
• T2 (Invite speakers) cannot start until T1 (Book venue) is completed.
• T4 (Promote the conference) can only start after T3 (Design
marketing materials) is done.
• T7 (Set up the venue) can only begin after T6 (Arrange catering) and
T5 (Register participants) are complete.
• T8 (Host the conference) is dependent on the completion of T7 (Set
up the venue).
Example of Key Components of Network Models
Nodes: Nodes represent tasks in network diagrams. They can be
visualized as circles or boxes. In our example, the nodes would be
labeled as follows:
• Node 1: Book venue (T1)
• Node 2: Invite speakers (T2)
• Node 3: Design marketing materials (T3)
• Node 4: Promote the conference (T4)
• Node 5: Register participants (T5)
• Node 6: Arrange catering (T6)
• Node 7: Set up the venue (T7)
• Node 8: Host the conference (T8)
Example of Key Components of Network Models
Objective:
• Learn how to apply PERT to manage projects with
uncertain task durations.
Program Evaluation and Review Technique (PERT)
Steps in PERT:
1. List Activities and Dependencies: Identify tasks and their
relationships.
2. Draw the Network Diagram: Visualize the tasks and dependencies.
3. Estimate Time: Use three estimates for each task duration:
1. Optimistic Time (O): The shortest time in which a task can be completed.
2. Pessimistic Time (P): The longest time in which a task can be completed.
3. Most Likely Time (M): The best estimate of the time required.
4. Calculate Expected Time (TE):
5. Determine the Critical Path: Identify the longest path using
expected times.
Program Evaluation and Review Technique (PERT)
Key Terms:
• Expected Time (TE): The weighted average of the
optimistic, most likely, and pessimistic times.
• Variance and Standard Deviation: Used to
measure the uncertainty in task durations.
Class Activity:
Exercise: Provide a set of project tasks with
optimistic, most likely, and pessimistic time estimates.
Have students calculate the expected times and
determine the critical path.
Project Task Set: Developing a Mobile App
• Here is a set of project tasks with optimistic, most
likely, and pessimistic time estimates. Students will
use this information to calculate the expected times
using PERT and determine the critical path.
Class Activity:
Example Solution
Example Solution