Professional Documents
Culture Documents
Betoniakatemia Betonilattiat.fi.en
Betoniakatemia Betonilattiat.fi.en
com
Concrete floors
Rudus Concrete Academy
HannuTimonen-Nissi
13.07.2024
Concrete floors
common
• In addition to the actual quality factors, the classification system has defined separately unclassified quality factors, which
are used, if necessary, according to the use requirements of the object.
• Unclassified quality factors include, for example, roughness (slipperiness), electrical conductivity, shelf life, chemical
resistance, color differences, the amount of fibers on the surface and other factors related to surface quality.
For classification markingcan, in the case of particularly demanding objects, be attached as a fourth partThe letter T.
2.12 Classification Marking
e.g. B – 3 – II
The classification mark defines the minimum quality level of each class.
In general, the aim should be to be as good as possiblequality level.
2.2 Use and application of the rating system
• Requirements regarding quality factors are set for each concrete floor as applicable.
• The requirement level of the quality factors, on the other hand, is determined by the use of the floor and is set by
the floor
in the planning phase.
• When setting the requirement level, the work method used to make the floor should also be taken into account.
• In the plans, the quality requirements must be presented in a complete combination according to the
classification,
for example B-4-II (T).
• The requirements for unclassified special quality factors are presented separately in the plan.
• The classification system is not capable due to the rather rough division of the quality requirements
to describequality requirements for all floors in detail.
• The purpose of the rating systemis to act as a guideline, and not quality requirements orrequirements
small undercuts should automatically be interpreted as meaning that the floor in question is fit for
purpose
unusable.
• Ifthe quality requirements are exceeded, the set oneslimit values of quality requirementsif possible,
3. Quality requirements for concrete floors
• When making concrete floors, the first thing to do is to make sure that the finished floor allows
in the spaceplanned operation, i.e. the quality requirements are determined by the intended use of the
floor
by.
When all functional quality requirements apply to the floor and its surface and
stresses are defined, analyzed and prioritized.
4. Floor coverings and –coatingsset requirements
4.1 Quality factors
• To be coatedor for the design, manufacturing method and post-treatment of the floor to be
coated
affect the following two author:
1) The stress on the floor, which means the floor from traffic and other use
targeting mechanical load.
2)Pavement/Coating.
Quality factors To the floor targeting The coating/coating
strain by by
Floor concrete X
moisture
Surface strength X X
Duration of cycling X X
Surface smoothness X
Surface smoothness X
Surface cleanliness X
4.2 Types of stress
• To the coatingor the stress on the coating is determined by the mode of use.
• The type of stress determines the quality requirements for the surface to be coated,
the strength of the surfaceand bike stressin terms of duration.
• The designerthe selected pavement type setsquality requirements of allin terms of
quality factors.
• Thusto be coatedquality requirements for concrete floorsdetermined by two parallel
factorsby.
5. Floor concrete reinforcement
• Steel fiber or structural plastic fiber ( macro fiber ) can be used to completely or partially replace traditional reinforcement
• Typical areas of use are underground floors, surface floors and piled slabs.
• It is now possible to use steel fibers also in load-bearing structures
• The share of fiber reinforcement is growing all the time
• Seams are usually the weakest point of a tile, so you should strive for floorswith as few seams as possible or seamlessto the floor.
• Seamsfor planningshould be attachedspecial attention and the type of seam should be chosen carefullyoperating conditionsrequirements in
accordance with.
• Sports seams
• Shrinkage seams
• Release seams
• Working seams
Adobe Acrobat
Document
7. Drying of floor concrete
7.1 Floor concrete and moisture
• The critical moisture value is the moisture value (coating limit value) that, taking into
account the measurement accuracy, must be below the judgment measurement depth
before coating or coating. This appliesspecially sensitive to moisture to the materials.
• Floor concrete moisture refers to the concrete slab and what may be on top of it
moisture content of screed.
• A screed applied on top of concrete that has dried on its surface re-wets the underlying
concrete, and this moisture and the moisture contained in the screed itself must be allowed
to dry before paving.getting started.
7.2 Measures affecting the drying of the concrete floor
• properties of concrete
• structural solution
• wetting of concreteduring construction
• drying conditions
• good drying conditions: relative humidity of the air in the room < 50%RH
and temperature>20 °C
• raising the temperature of the structure: heating the concrete is usuallymore efficient
drying methodlike heating the air surrounding the concrete
•floor surface grindingandsanitation.
8. Concrete floor implementation instructions
8.1 Kick-off meeting and reception of the work area
• The meetingthe primary goal is to ensure quality by going through the issues related to the
contract so that all parties have a clear and uniform understanding of the issues related to the
execution of the work.
At the kick-off meetingthe following matters are discussed to the necessary extent:
• plans and documents drawn up for the work (work reports, drawings)
•job- andliability limits
•quality requirements(also unclassified Quality factors)
•quality to state used methods
• the contractor's quality system or site-specific quality plan
•of concrete characteristics
•casting conditionsandweather protection need
•material deliveriesandstorage
• driving routes, work schedule and concreting plan, including concretemove,of concrete
sealing method, surface finishing and aftercare procedures
• supplying factories, preparation for disruptions (spare factory, spare pump), delivery speed
• structural details and special precision or unusual work technique
require points
•schedule
• connection of the contract to other work phases of the construction site
•responsible persons and contact information
• persons who decide on tasks and changes that deviate from plans during work
•the contractor to be answered those quality documents
• commissioning of the floor (loading, other work steps)
• floor maintenance instructions and delivery to the customer.
Kick-off meeting…
• Minutes of the meeting are drawn up and signed by the customer and the contractor.
• Floor work the starting point for planning is the contract program and general schedule of the
entire construction site.
• The floor you have to allow time for doing it so that there is also enough time for the post-
treatment and drying of the concrete and the floor is not loaded too early.
• Daily the amount of work is matched to the joint distribution according to the plans as well as
possible.
• Floor workin the timing it must be taken into account that the highthe achievement of quality
requirements ismore difficult in winter conditions than in warm conditions.
At the reception of the work area, the flooring contractor and the customer inspect
together
about the base of the future floor, the surrounding workspace and the prepared plans
The choice of work method is based onthat I'm donethe floor must be filledplanned for the destination
of useset requirements.
So that everyone's end resultinfluential partieswould be the samea unified understanding of these
requirements, definesthe quality level of the features that the designer considers to be the most important.
The definition is based on unequivocal explanationsmeasurement andto testing methods orthe appropriate testing
method
in the absence of something elseto the quality deemed appropriateevaluation method.
Affecting the choice of work methodfactors are e.g:
• The choice of concrete mass is based on the ready-madeto those placed on the floorto quality
requirements andto the selected work technique.
• However, the quality of the floor is created in many different waysfrom the combined effect of
the factor.
• The whole that leads to a good result isof different componentsoptimal combination.
• Strength
• Maximum grain size
• Wear resistance of the body material
• The quality of the binder
• Water-cement ratio
• Suppleness
• Shrinkage magnitude / crack control
• Pouring temperature of concrete
8.4 Temperature
• Concreting spacethe right air temperature (at least +10 degrees)near the floor lineis important.
• Special attentionshould be attached to the corners andto the doorways.
• Especially on thin floors, the temperature of the concrete mass dropsquickly casting platform(gravel,
concrete) temperature
according toand airspacestrong heatingduring the casting degrades important bonding andhardening
initial stagereactions and aftermath.
• All rightconditions, the best results are obtained with a cool air (15...20 C) by mass.
• respectivelytemperature increase from +20 degrees+to 30 degreescuts the engagement time in half.
9. Correct implementation of a concrete floor
Sizeduring the project: In the implementation phase:
• closecooperation, "intact chain" • rightwork performance
• tightcontrol • uniform qualitymass
• of qualitybe ready to pay • ladiesconditions
• fitcasting areas
• carefulaftercare
Beforecasting:
• carefulplanning and dimensioning Castingsafter:
• platformcheck • carefulaftercare
• ladiesconditions • Notoo early loading
• successfulmass selection • Nocoating too early
HannuTimonen-Nissi
hannu.timonen-nissi@rudus.fi
www.rudus.fi