Professional Documents
Culture Documents
CCPM 1.0
CCPM 1.0
CCPM 1.0
Critical Chain Project Management
WHAT IS PROJECT MANAGEMENT
What is a Project
Representing Activities
CRITICAL PATH METHOD
Forward Pass
CRITICAL PATH METHOD
Backward Pass
CONCEPT OF FLOAT
What is Float?
The term "float" refers to the amount of time that a task can be delayed without causing a delay to subsequent
dependent tasks or the project's overall completion date. It is also known as "slack" or "buffer." Float is an
essential concept in project scheduling and critical path analysis.
Total Float (TF): Total float is the amount of time that a task can be delayed without delaying the project's
completion date. Tasks with total float can be delayed without impacting the project's schedule as long as they
are completed within their float time.
Free Float (FF): Free float is the amount of time that a task can be delayed without delaying the early start of any
successor task. It represents the flexibility available to a specific task without impacting the start of subsequent
dependent tasks.
Float calculation is crucial for project managers to identify tasks that are critical to the project's timeline (those
with zero float), as well as those with float, which can be delayed without affecting the overall project schedule.
This information helps in prioritizing tasks, resource allocation, and managing project risks.
Calculating Floats
FINDING OUT CRITICAL PATH IN NETWORK
DIAGRAM
CRITICAL PATH
Start-to-Finish (SF) - Start the predecessor when the successor completes (rarely used)
FOUR RELATIONSHIPS BETWEEN TASKS : FS
Finish-to-Start (FS) : The initiation of the successor activity depends upon the
completion of the predecessor activity.
Finish Start
Task A Task B
FOUR RELATIONSHIPS BETWEEN TASKS : FF
Finish-to-Finish (FF) : The completion of the successor activity depends upon the
completion of the predecessor activity.
Finish
Task A
Task B
Finish+ Lag
FOUR RELATIONSHIPS BETWEEN TASKS : SS
Start-to-Start (SS) : The initiation of the work successor activity depends upon the
initiation of the predecessor activity.
Start
Task A
Task B
Start +lag
FOUR RELATIONSHIPS BETWEEN TASKS : SF
Start-to-Finish (SF) : The completion of the successor activity depends upon the
completion of the predecessor activity.
Start
Task A
Task B
Finish
REASONS OF DELAY IN PROJECT
REASONS OF DELAY
1. Student Syndrome – The term "student syndrome" refers to a phenomenon where individuals
tend to procrastinate and delay their work until the last possible moment, often waiting until just
before a deadline to start or complete tasks.
2. Early Finish vs Late Finish – Delay is transferred in case of late finish, Early finish is wasted
3. Multitasking – Resources loaded beyond capacity => Higher cycle time & reduced throughput
4. Parkinson’s Law – Work expands to fill available time. In other words, if you give yourself a certain
amount of time to complete a task, you'll likely take all that time to finish it, regardless of the actual
amount of work involved.
5. Fixed Date Plan - A fixed date plan refers to a project schedule where the completion date is fixed
and cannot be changed. This type of plan is typically used when there are external dependencies or
constraints that dictate a specific deadline, such as contractual obligations, regulatory
requirements, or events with fixed dates.
CCPM SOLUTION
WHAT MANAGEMENT PROCESSES DO YOU NEED
1.Buffer Management
2.Full Kitting
3.Pipelining
4.Maintaining LOW WIP
BUFFER
1. Risk Mitigation
2. Flexibility and Adaptability
3. Improved Performance
4. Enhanced Stakeholder Satisfaction
5. Facilitated Decision-Making
6. Increased Resilience
FULL KIT
• Having all the necessary tools, resources, and components to successfully execute a
project.
PIPELINING