• Polavaram Irrigation Project Left Main Canal is one of the important components of Polavaram Irrigation
Project.
• It is intended to create an Irrigation potential of 4.00 Lakh acres throughout the length of canal
• To divert 23.44 TMC of Godavari Water to Visakhapatnam industrial requirements and to provide drinking
water to the enroute villages.
• Overview of PIPLMC: 210.927 KM
1. Length of the canal (Duly deleting Pampa, Thandava, Varaha Aqueduct lengths i.e 2.565 kms )
358 Villages
2. Water supply to for Drinking and Industries 23.44TMC
in Vizag
3. Ayacut development 4.00 Lakh acres.
East Godavari District: 0.81 Lakh acres, Kakinada District: 1.67 Lakh acres
Konaseema District: 0.02 Lakh acres, Anakapalli District: 1.50 Lakh acres
Km.25.600
Km51.600
discharge 1360 Cumecs is in
Km.69.145
Km.93.700
Km.0.00
Progress 55.410, km64.375 are in progress. 2)Pampa @91.700 discharge 1390
progress
Cumecs is in progress.
RIVER GODAVARI
Held up
Package No. V Package No. VII
due to Package No. VI
R&R .
Km.162.409
NH @ 103.658
Km.110.159
Tandava Aqueduct
Km.136.000
Km.111.000+
Km.93.700
Km.112.223
1.351
MGR
1)Railway Crossing
Package No. VIII.
proposals to be
Km.10.650 @ KM5.2
Pipe line
finalised
2)NH Crossing @ KM
NEW WATER SUPPLY 0.850
Km.4.600
CANAL
INDEX
Km.0.000
Entrustment of Balance works
PIPLMC Canal , EXISTING WATER SUPPLY CANAL
KBR Railway Crossing (2 No’s)
Km.162.409 Km.173.309 NH Crossing (11 No’s)
1)Railway Crossing @173.421
2)NH Crossing @173.609 Major Crossings (7 No’s)
NEW IRRIGATION CANAL
Sarada syphon at KM Land to be Acquired
Km.176.209 32.3151 Acres of Land to be 175.184
handed over from KM
Km.177.809 176.209 to 177.809
Note:- Proposals for entrustment of balance works were submitted to the Government. Orders are awaited
Polavaram Irrigation Project Left Main Canal From KM 25.600 to 51.600-1.459
Package 2
Km.25.600
KM 33.559
Km.41.560
Km51.600
Package 3
Package 1
Package No. II
Kakinada Dt & East Godavari Dt.
Status
S.No Type of Structure Nos
Completed Progress Not tackled Deletion
1 Super Passage 9 9 0 0 0
2 SLRB 3 3 0 0 0
3 DLRB 2 2 0 0 0
4 SP & SLRB/DLRB 16 16 0 0 0
5 Cross Regulator 2 2 0 0 0
6 Off Take 8 8 0 0 0
7 NH Crossings 2 1 1 0 0
INDEX
Completed
Status
Total
S.No Description Length NH Crossing (2 No’s)
Completed Progress Not Tackled Partially
Completed
Note:- 1. Proposals for entrustment of balance works were submitted to the Government. Orders are awaited
2. VISCWO pipeline closure is required for shifting of pipeline at 3 different locations i.e., at Km: 52.582,
Km:54.045 and Km:55.378. Balance works of VISCWO pipeline crossings are yet to be entrusted.
Note:- Proposals for entrustment of balance works were submitted to the Government. Orders are awaited
POLAVARAM IRRIGATION PROJECT - LEFT MAIN CANAL - PACKAGE-6
FROM KM 111.000 – KM 136.000+0.780
CRITICAL ISSUES
ANAKAPALLI DISTRICT
PIPLMC PACKAGE-5
PIPLMC PACKAGE-7
PACKAGE-6
126.733
CR
Km.136.780
Km.111.000
Note:- Proposals for entrustment of balance works were submitted to the Government. Orders are awaited
POLAVARAM IRRIGATION PROJECT - LEFT MAIN CANAL - PACKAGE-7
FROM KM 136.000 – KM 162.409
CRITICAL ISSUES
ANAKAPALLI DISTRICT
SURPLUS ESCAPE
Narsipatnam-
SP cum SLB
SP cum SLB
Addaraod LA for 7.30 Acres
Diversion Road required
PIPLMC PACKAGE-6
PIPLMC PACKAGE-8
DLRB
SLRB
AQUEDUCT
SP
SP
SP
SP
KM 138.399
KM 138.507
KM 139.750
KM 162.00 to
KM 138.025
KM 161.480
KM 139.175
KM 139.220
KM.136.000
KM 150.975
KM 160.270
KM 148.742
KM 143.950
KM 162.409
KM 161.920
KM 147.493
KM 162.200
KM 160.630
EXECUTION STATUS OF CM&CD WORKS
STATUS (LENGTH IN KM)
TYPE OF TOTAL LENGTH
TOTAL COMPLETED IN PROGRESS NOT GROUNDED S.NO DESCRIPTION
STRUCTURE in KM
SLRB 8 7 0 1 COMPLETED PROGRESS
Under
Tunnels
19 17 2 0 INDEX
SP Cum SLRB 8 0 7 1 COMPLETED
IN PROGRESS
Offtakes 17 9 7 1
CRITICAL ISSUE 1)Narsipatnam-Addaroad Diversion Road
Escape cum
Regulator 1 0 0 1 submitted to Government 2) Land Acquisition is required for
completing the Embankment.
Aqueduct 1 0 1 0 TO BE TACKLED
Footbridge 1 0 0 1
Total 65 35 22 8
BALANCE WORKS OF PACKAGE-8 VISAKHAPATNAM DISTRICT
PENDURTHI
MGR
PARWADA
MANDAL
MANDAL
1.0TMC
KASIMKOTA
MANDAL
11.00 Km
ANAKAPALLI DISTRICT
SLB 172.285 KM
SLB 169.712 KM
SP 168.498 KM
Railway crossing @5.20 km of
167.627 Km
162.409 Km
170.805 Km
170.839 Km
NWSC
162.509 Km
173.250 Km
173.309 Km
166.855 Km
Q = 3.00 Cumecs
10.90 Km
20.347 Km
20.767 Km
2.22 Km
31.609 Km
20.955 Km
21.237 Km
24.000 Km
28.000 Km
24.809 Km
11.804 Km
32.939 Km
33.20 Km
20.30 Km
19.79 Km
14.50 Km
PACKAGE-8B
NH crossing @0.85 km of NWSC
0.00 Km
LMC PACKAGE-7
3.25 m 3.40 m
200 m
12 m 4.25 m 3.5 m 4.25 m 3.40 m 3.25 m
BW: 53.0 m 12.5 m 9m
33.609 Km
WATER SUPPLY CANAL Railway crossing @173.421 km of NIC
16 m EXISTING WATER SUPPLY CANAL
Q = 55.230 Cumecs NH crossing @173.609 km of NIC KBR
Q = 24.00 Cumecs
0.50TMC
PACKAGE-8A
Sarada syphon @174.697 km to 175.238 km of NIC
69R Melupaka @175.285 km OT of NIC
70TE Pudimadka @177.809 km OT of NIC
177.809 Km
NEW IRRIGATION CANAL
Q =30.08 Cumecs
INDEX
COMPLETED
PACKAGE-8A, 8B (CRITICAL TO BE
TENDERED)
Reservoirs
NOTE: 1. Proposals for entrustment of balance works were submitted to the Government. Orders are awaited
2. The estimate for Rs74.80 Crores with current SSR for package 8B is submitted and is under scrutiny at Competent authorities.
SUMMARY – STATUS OF WORKS
Earthwork Canal Lining
EWE (KMs) PKg. 1 PKg. 2 PKg. 3 PKg. 4 PKg. 5 PKg. 6 PKg. 7 PKg. 8 TOTAL
Completed- Total 25.82 24.23 19.63 25.96 18.51 25.78 23.39 48.80 212.12
81%
Pending-19%
Completed 19.40 24.23 18.89 24.62 15.79 21.73 22.10 25.40 172.15
Balance 6.42 0.00 0.74 1.34 2.72 4.05 1.29 23.40 39.97
Canal Lining
Lining (KMs) PKg. 1 PKg. 2 PKg. 3 PKg. 4 PKg. 5 PKg. 6 PKg. 7 PKg. 8 TOTAL
Completed- Total 25.821 24.227 19.03 25.934 18.511 25.78 23.393 48.804 211.5
62%
Pending-37% Completed 15.28 24.227 14.725 20.305 10.397 18.521 18.926 9.6 131.981
Balance 10.541 0 4.305 5.629 8.114 7.259 4.467 39.204 79.519
Structures
Structures(Nos) PKg. 1 PKg. 2 PKg. 3 PKg. 4 PKg. 5 PKg. 6 PKg. 7 PKg. 8 TOTAL
Completed-
Total 50 42 47 47 47 71 65 82 451
41% Completed 29 40 36 0 17 18 38 9 187
Pending-31%
Progress 17 2 9 26 9 7 19 0 89
Balance 4 0 2 21 21 46 8 73 175