SMART IN FLOW CONTROL

Issues we are facing

PRODUCTION TEAM
SMART IN FLOW CONTROL

Planning team are making Internal work order in SJO’s

PRODUCTION TEAM
SMART IN FLOW CONTROL

Child items get allocated automatically in auto allocation due to that we


don’t get material to make work orders.

PRODUCTION TEAM
SMART IN FLOW CONTROL

MORE THAN 2 MONTH DELAY IN MATERIAL AND DELAYED PO CONVERSION

PRODUCTION TEAM
SMART IN FLOW CONTROL

RAW MATERIAL REQUIRED FOR INVOICING PLAN IS NOT BEING


FULFILLED FOR THE SAME MONTH

For Ex:
700 Cm2 Bottom Covers Received less than requirement to june months plan

CASTING NUTS OF JUNE INVOICING


PLAN RECEIVED ON 07/07/2022.

PRODUCTION TEAM
SMART IN FLOW CONTROL

Other Problems we are facing :


1. CCN Items due to that stock will get mismatched and
increasing in WIP inventory

2. We need processing time of 2-3 days especially for


covers and casting nut due to outside Plating/machining.

PRODUCTION TEAM
SMART IN FLOW CONTROL

Thank you!

PRODUCTION TEAM