L4-Developing a Project Plan
L4-Developing a Project Plan
L4-Developing a Project Plan
Plan (Network)
BITS Pilani M K Hamirwasia
Pilani Campus WILPD
BITS Pilani
Pilani Campus
ET ZC423/PE ZC423-Merged
Essentials of Project Management
Lecture No. 04
BITS Pilani, Deemed to be University under Section 3 of UGC Act, 1956
Activity-on-Node
Fundamentals
• Total Slack
The amount of time an activity can be delayed and not delay
the project
• Free Slack
The amount of time an activity can be delayed without delaying
any immediately following activity
• Sensitivity
– Reflects the likelihood the original critical path(s) will
change once the project is initiated.
Insensitive and Sensitive network
7 C 11
0 Rf
7 4 11
0 A 3 3 B 7 7 D 8 11 G 13 13 I 15 15 J 16
0F
0 Pr Fn 0 Er Fr 3 Win 0 RiF 0 Pt 0 Cp
0 3 3 3 4 7 10 1 11 11 2 13 13 2 15 15 1 1
7 E 8 10 H 11
3 Drs 2 DO
10 1 11 12 1 13
CP: A-B-C-G-I-J
FS (H) = 2 7 F 10 TE = 16 Days
1 El
8 3 11 BITS Pilani, Pilani Campus
Exercise
2 B 3 3 E 5 5 H 6
TE = 9 Days
0 SSAD 0 PRA 0 SSAT
2 1 3 3 2 5 5 1 6 3 Critical Paths
Very Sensitive
Network
0 A 2 2 C 3 3 F 5 5 I 6 6 K 8 8 L 9
0 SD 0 SSBD 0 PRB 0 SSBT 0 Intgrn 0 InTst
0 2 2 2 1 3 3 2 5 5 1 6 6 2 8 8 1 9
2 D 3 3 G 5 5 J 6
0 SSCD 0 PRC 0 SSCT No Free Slack
2 1 3 3 2 5 5 1 6
BITS Pilani, Pilani Campus
Developing a Project Plan
Thank You!
M K Hamirwasia