Sh Nti Tanjung Karang Report_13042023_#02

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 17

NTI CO – SH TANJUNG

KARANG PROGRESS REPORT


#02

Weekly Report : 07/04/2023 – 13/04/2023)


Infinite Project Management
NTI TANJUNG KARANG
NTI CO – SH TG KARANG PROGRESS REPORT #02
Content
 1.0 - Contract Details
 2.0 - Physical Progress
 3.1 - Major Task Progress
 4.1 - Manpower Planning & Allocation
 4.2 - Machineries Planning & Allocation
 5.0 - Issues Arising
 5.1 - NCR Status
 5.2 - Cost Report – VO
 6.0 - Handover Status
 7.0 - Site Progress Photo
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
1.0 Contract Details
Contract No.
Contractor Infinite Project Management
Date of Letter of Award (LOA)
Date of Acceptance of LOA
Site Possession Date 24/2/2023
Contract Completion Date
Revised Contract Completion Date
Contract Duration
Contract Value
Estimated Contract Value N/A
Liquidated Ascertained Damages (LAD) (RM/day) 5,000.00
Defect Liability Period (DLP) 1 Year
Gross Certified Payment N/A
Gross Payment to date N/A
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
2.0 Physical Progress
Progress Status (Revised Baseline Program - 152 Days)

Baseline (%) Actual (%) Delay Critical Works (Driving Activities)


• Piling Work: (Building 100%, Retaining Wall
60%, Main Canopy 100%, Tank Farm 100%)
Construction
14% 9% 5% (24 days) • Raft Foundation Preparation Work
(Mitigated)
• Bricklaying Work For Retaining Wall

Contract Completion Date:


Expected Completion Date: 12/9/2023
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
3.1 Major Task Progress
Major Task Status (A Week Look-Ahead)
This Week (07/04/23 - 13/04/23) Status Remarks

Delay of piling work near Pak Sani house for


Piling Work for main canopy area On going
retaining wall, skysign and compact

Building Raft Foundation Preparation On going Concreting work on Saturday 15/4/2023

Retaining Wall Bricklaying Work On going

Next Week (14/04/23 - 20/04/23) Status Remarks

Concrete Cast Of Building Ground Slab Ongoing 1 Day Early From Schedule

Separate Team To Focus On Retaining Wall


Retaining Wall work Ongoing
Construction Only
Work Being Done Before Raya Instead Of After
Sheet piling work for tank farm Ongoing
Raya Holiday
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
4.1 Manpower Allocation & Planning
For The Week
Sub-total
No Resources F S S M T W T
07/04 08/04 09/04 10/04 11/04 12/04 13/04
P A P A P A P A P A P A P A P A

1.1 Project Manager

1.2 Construction Manager 2 2 2 2 2 2 2


1.3 Permit Holder 1 1 1 1 1 1 1
1.4 Safety & Health Officer 1 1 1 1 1 1 1
1.5 General Worker 7 7 7 7 7 7 9
1.6 Carpentry Work

1.7 Piling Work 2 2 2 2 2 2


1.8 Excavator 1 1 1 1 1 1 1
1.9 Security 4 4 4 4 4 4 4
1.10

Total No. of Manpower


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
4.2 Machineries Allocation & Planning
For The Week
Sub-
F S S M T W T
No Resources total
07/04 08/04 09/04 10/04 11/04 12/04 13/4

P A P A P A P A P A P A P A P A

1. Excavator 1 1 1 1 1 1 1
2. Piling Machine 1 1 1 1 1 1
3. Bar Bending Machine
4. Bar Cutting Machine
5. Crane 1
6. 1 Tonne Roller
Total No of Machineries 2 2 1 2 3 2 2
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
5.0 Issue Arising

Critical Issues
Action/
No. Date Impact/ Effect
Description Cause Final Date
Reported
1 Pending Pak 8/4/2023 Pak Sani did not allow any Delay in Piling work S.I received on 4th April pending
Sani’s access road work on his boundary until near the housing area on the date of work to be start
shift and TNB get assurance/reply from
pole relocation Shell legal team
work

2 Pending 13/4/2023 New MVI design require Delay in Canopy Discussion has been made with
confirmation of 600mm fascia height which structure fabrication and Mht Design team and Nadi
canopy fascia hard to achieve installation Consult. No exact date to be
height conclude yet because both parties
need to study on the proposed
design
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
5.1 NCR Status

NCRs
Action/
No. NCR Descriptio Date Action Proposed Closing Status
Referen Reporte Non-Compliance Date
n
ce d
1

2
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
5.2 Cost Report – Variation Order (VO) Works

VOs Impact/ Effect


Status
SI/EI/AI Date (Approved/
No. Description Cost (RM) Time
Reference Submitted Rejected)

1
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
6.0 Handover Status

ITEM PAYMENT / FEE T&C Planned Actual REMARKS


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Concrete Cast Of Retaining Wall Base


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Piling Work For Main Canopy (Completed)


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Piling Work Of Tank Farm area


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Install Formwork For Raft Foundation, Install Toilet


Sewerage Pipeline, RWDP, Electrical Manhole, Telekom
Manhole etc
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Install Formwork For Raft Foundation, Install Toilet


Sewerage Pipeline, RWDP, Electrical Manhole, Telekom
Manhole etc
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #02
Weekly Report : (07/04/2023 – 13/04/2023)
7.0 Site Progress Photos

Photo Description

Lay BRC For Building Raft Foundation