NTI CO – SH TANJUNG

KARANG PROGRESS REPORT


#16

Weekly Report : 09/06/2023 – 15/06/2023)


Infinite Project Management
NTI TANJUNG KARANG
NTI CO – SH TG KARANG PROGRESS REPORT #16
Content
 1.0 - Contract Details
 2.0 - Physical Progress
 3.1 - Major Task Progress
 4.1 - Manpower Planning & Allocation
 4.2 - Machineries Planning & Allocation
 5.0 - Issues Arising
 5.1 - NCR Status
 5.2 - Cost Report – VO
 6.0 - Handover Status
 7.0 - Site Progress Photo
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
1.0 Contract Details
Contract No.
Contractor Infinite Project Management
Date of Letter of Award (LOA)
Date of Acceptance of LOA
Site Possession Date 24/2/2023
Contract Completion Date
Revised Contract Completion Date
Contract Duration
Contract Value
Estimated Contract Value N/A
Liquidated Ascertained Damages (LAD) (RM/day) 5,000.00
Defect Liability Period (DLP) 1 Year
Gross Certified Payment N/A
Gross Payment to date N/A
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
2.0 Physical Progress
Progress Status (Revised Baseline Program - 164 Days)

Baseline (%) Actual (%) Delay Critical Works (Driving Activities)


• Bricklaying Work Of Shop Building
• Main Canopy Steel Structure Erection
• Construct OSD
Construction
24% 23% 1% • Perimeter Drainage Work
(Mitigated)
• RWDP installation
• TNB & Telekom manhole installation

Contract Completion Date:


Expected Completion Date: 24/8/2023
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
3.1 Major Task Progress
Major Task Status (A Week Look-Ahead)
This Week (09/06/2023 - 15/06/2023) Status Remarks

50% completed. Separate team to expedite


Brick laying work for shop building On going
progress

80% done. Pending round edge fascia


Main canopy structure installation On going
installation as need to measure on site

RWDP installation On going Use precast manhole to expedite progress

Separate team focusing on rebar work and


Construct OSD On going
concreting work
Using precast manhole. All corrugated pipe
TNB & Telekom Manhole installation Completed installed and done backfilling work. TNB pipe
stop at pak sani house area
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
3.1 Major Task Progress
Major Task Status (A Week Look-Ahead)

Next Week (16/06/2023 - 22/06/2023) Status Remarks

OSD construction work On going Separate team to expedite progress

Main canopy steel structure installation On going Touch up work required

Fuel system work On going Titan materials received on 14/6/23

Canopy roof installation, gutter & etc Planning Separate team for roof installation

Separate team and adding more worker to


Bricklying work (shop building) On going
expedite work progress
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
4.1 Manpower Allocation & Planning
For The Week
Sub-total
No F S S M T W T
Resources
09/06 10/06 11/06 12/06 13/06 14/06 15/06
P A P A P A P A P A P A P A P A

1.1 Project Manager 1


1.2 Construction Manager 2 2 2 2 2 2
1.3 Site Supervisor 1 1 1 1 1 1
1.4 Permit Holder 1 1 1 1 1 1
1.5 Safety & Health Officer 1 1 1 1 1 1
1.6 Skilled Worker 11 11 11 11 11 11
1.7 Brickmasons
1.8 Helper 11 12 12 12 12 12
1.9 Excavator operator 1 1 1 1 1 1
1.10 Security 3 3 3 3 3 3
1.11 Operator (Backhoe,
4 4 3 3 3 3
Crane,Skylift)
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
4.2 Machineries Allocation & Planning
For The Week
Sub-
F S S M T W T
No Resources total
09/06 10/06 11/06 12/06 13/06 14/06 15/06

P A P A P A P A P A P A P A P A

1. Excavator 1 1 1 1 1 1
2. Backhoe
3. Crane 1 1 1 1 1 1
4. Skylift 2 2 2 2 2 2
5.
6.
Total No of Machineries 4 4 4 4 4 4
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
5.0 Issue Arising

Critical Issues
Action/
No. Date Impact/ Effect
Description Cause Final Date
Reported
1

2
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
5.1 NCR Status

NCRs
Action/
No. NCR Date Non- Action Proposed Closing Status
Description Date
Reference Reported Compliance
1

2
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
5.2 Cost Report – Variation Order (VO) Works

VOs Impact/ Effect


Status
SI/EI/AI Date (Approved/
No. Description Cost (RM) Time
Reference Submitted Rejected)

1 SI/22.8057/ Duration and completion 24/2/2023


IPM/2023/002 date

2 SI/22.8057/ IPM to construct item as per 24/3/2023


IPM/2023/002 mentioned in MDKS
approval letter

3 SI/22.8057/ Relocation of jalan masuk 24/3/2023


IPM/2023/001 Pak Sani

4 SI – BG IPM need to apply bank 31/5/2023 RM20,000 Approved


Payment for guarantee for TNB CSP
TNB approval
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
5.3 Request For Information (RFI)

No. Tittle Description Submitted To Date Action date

List of few item need Discussion on the OTP element


1 List of RFI MHT 22/2/23 18/4/23
confirmation with MHT design and project team

Vent Stack Vent stack location near MHT Design team revised FFS
2 MHT 2/3/23 22/5/23
location to Pak Sani house drawing to relocate vent stack

To proceed with shell


3 Shell cafe MHT 18/5/23 Pending shell café layout drawing
café lite spec

Tanker Concern In Future The Design Team Has Confirmed To


Discharge Paint Peel Off The MHT 26/5/23 Proceed As Per Latest FYS 30/5/23
4
Aluminum Plate Aluminum Plate Drawing
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
6.0 Weather Chart (a week)

Date
1 2 3 4 5 6 7 8 9 10 11 12 Total hours
Am
9/6/23
Pm
Am
10/6/23 Pm
Am
11/6/23 Pm
Am
12/6/23 Pm
Am
13/6/23 Pm
Am
14/6/23 Pm
Am
15/6/23 Pm
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 QHSSE (Audit Findings, Inspection)

No. Finding/Inspection Date By Action Due Date


NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description
NTI CO – SH TANJUNG KARANG PROGRESS REPORT #16
Weekly Report : (09/06/2023 – 15/06/2023)
7.0 Site Progress Photos

Photo Description

You might also like