Project : DTA – EX – WAREHOUSE Date :

19-10-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building)
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s

1 Project manager Helper 2

2 Project In charge 1 Fitter 1


3 Execution Engineer Welder 1

4 Planning Engineer Painter


5 Billing In charge Electrician 1

6 Billing Engineer

7 Quality Engineer

8 Contracts

9 Admin

10 Store In charge

11 Purchase

12 Accounts

13 Safety Asst.

2
2
FAS & PA Facility AdditionalTeam Requirements
S.No Description Remarks
1 Zone wise PA drawings required As build Inputs Taken Soft Copy Shared

2 Above mezzanine floor AHU Room PA speaker to be provided - Additional Will be Done Along Second Layer Work
requirement
3 Zone wise PA speaker count to be provided in drawing As build Inputs Taken Soft Copy Shared

4 Rest rooms to be provided with Sounders. - additional requirement. Material Ordered will be Delivered in
22ndOctober
5 Transformer & HT panel rooms to be provided with MCP & Sounders - Material Ordered will be Delivered in
Additional requirement 22ndOctober
6 FAS panel room detectors & Sounders - additional requirement -

7 Repeater panel location to be confirmed by Flex Confirmed Cabling will be Started &
Finish it on 31-Oct -20
8 Beam detector approach requested by Flex facility team -

9 Approaching cable to beam detectors be laid in cable tray -

3
Pump Room Material Delivery Schedule
Sl. No Activities Description Start Date End Date Current Status as on date
Pump Room

1 24-Nov-20 30- Nov-20 • Order Placed


Pump Delivery ( All Pumps)
2 • Delivered
15-Nov-20 25-Nov-20
FM Gate Valves , NRV, Strainer
3 • Ready before Work start Will be reached
15-Nov-20 20-Nov-20
Pipes
4 20-Nov -20 25-Nov-20
Measuring Instruments
5 25- Nov-20 30-Nov-20
Aluminum Cable From Fire Panel to Pump
6 15-Nov-20 20-Nov-20
Weldable Accessories
7 25-Nov -20 10-Dec-20
Installation Work
8 25-Nov-20 30-Nov-20
PRV , Flow Meter
9
Panel Delivery

4
Ware House – Shutdown Work Work & Balance Work
Activities Description Start Date End Date Current Status as on date
Shutdown Work
1 Old Ware Sprinkler House Raiser & Hydrant Modification 19-Sep-20 20-Sep-20 • Completed
Work
2 Zone -2 Branch Pipe Vertical Pipe Modification 11-Sep-20 12-Sep-20 • Completed
3 Zone -2 Drain Line Taping with Sprinkler Header 11-Sep-20 12-Sep-20 • Completed
4 11-Sep-20 12-Sep-20 • Completed
Zone -2&4 Below Mezzanine Header Connection
5 Bus Parking Hydrant Post Modification • Completed
6 External Hydrant Close Loop Tapping 17-Oct-20 18-Oct-20 • Fabrication done
7 Back Loading Bay Valve Installation 11-Sep-20 12-Sep-20 • Completed
8 Zone 2&4 Flow Switch Installation 17-Oct-20 18-Oct-20
9 Zone -2&4 Above Mezzanine Header Connection 17-Oct-20 18-Oct-20
• Fabrication Completed

10 17-Oct-20 18-Oct-20 • Installed & Completed


Above Mezzanine BF Valve Installation for Isolation
11 17-Oct-20 18-Oct-20 • Fabrication Completed Tapping Balance
Water Monitor & Fire Brigade Installation

5
Progress Pictures - Above Mezzanine Sprinkler

Above Mezzanine Below to Above Internal


Sprinkler Header Hydrant Tapping
Tapping Pipe

1st & 2nd Layer 150mm


Isolation Valve
6
Progress Pictures - Above Mezzanine

External Hydrant Final Painting Completed


till UPS Room include support Painting
Further area Wall Painting not completed

4 Way Fire Brigade


7
Fabrication
Pending Works Over All FPS/FAPA
Sl. Activities Description Start Date End Date Current Status as on date
No

` • Completed
17-Sep-20 22-Sep-20
Internal Hydrant Hose Box Fixing for Zone-3,4& Below Mezz
2 23-Sep-20 • Completed
15-Sep-20
Above Mezzanine 1 Layer Sprinkler
st
10 - Oct-20
3 25-Sep -20 • Header Erection Completed
19-Sep-20
Above Mezzanine Hydrant System with Accessories 25-Oct-20
4 • Waiting for the Additional balance Reflector
Beam Device Re – Commissioning – 4 Nos

5 Canteen Sprinkler - Work • Header Work Stared


6 External Hydrant Pipeline at Chemical Room • Completed
7 Above Mezzanine 1st Layer Sprinkle • Completed

8 • Waiting for the Support Clearance Pipe


Above Mezzanine Second Layer Sprinkler Erection Work 05-Oct -20 25- Oct-20 Fabrication Stared

9 FAPA Demo and Hand Over with Warehouse Team 19-Sep-20 19-Sep-20 • Completed
26-Sep-20 26-sep-20
10 System Identification (Painting/Sticker)
12-Oct -20 14- Oct -20

11 Hydrant hose box – 13 Nos 12-Oct-20 16-Oct-20 • Completed


12 12-Oct-20 16-Oct-20 • 1 Nos Completed
250NB Gate Valve – 2 Nos fixing
8
13 • Till UPS Room Completed Further Wall
12-Oct -20 17-Oct -20 Painting not Finished
Progress Pictures

Above Mezzanine 2nd Layer Sprinkler


Fabrication Work Priming Work
Above Mezzanine 2nd Layer Sprinkler
Fabrication Work Pipe Shifted to
location
9
Progress Pictures

Canteen Sprinkler Tapping Connection from


above Mezzanine

External Hydrant
Support Painted
10
Progress Pictures

Wall Painting Not yet


Completed

11
Thank You

12