Fps & Fapa - 19th Oct
Fps & Fapa - 19th Oct
19-10-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building)
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s
6 Billing Engineer
7 Quality Engineer
8 Contracts
9 Admin
10 Store In charge
11 Purchase
12 Accounts
13 Safety Asst.
2
2
FAS & PA Facility AdditionalTeam Requirements
S.No Description Remarks
1 Zone wise PA drawings required As build Inputs Taken Soft Copy Shared
2 Above mezzanine floor AHU Room PA speaker to be provided - Additional Will be Done Along Second Layer Work
requirement
3 Zone wise PA speaker count to be provided in drawing As build Inputs Taken Soft Copy Shared
4 Rest rooms to be provided with Sounders. - additional requirement. Material Ordered will be Delivered in
22ndOctober
5 Transformer & HT panel rooms to be provided with MCP & Sounders - Material Ordered will be Delivered in
Additional requirement 22ndOctober
6 FAS panel room detectors & Sounders - additional requirement -
7 Repeater panel location to be confirmed by Flex Confirmed Cabling will be Started &
Finish it on 31-Oct -20
8 Beam detector approach requested by Flex facility team -
3
Pump Room Material Delivery Schedule
Sl. No Activities Description Start Date End Date Current Status as on date
Pump Room
4
Ware House – Shutdown Work Work & Balance Work
Activities Description Start Date End Date Current Status as on date
Shutdown Work
1 Old Ware Sprinkler House Raiser & Hydrant Modification 19-Sep-20 20-Sep-20 • Completed
Work
2 Zone -2 Branch Pipe Vertical Pipe Modification 11-Sep-20 12-Sep-20 • Completed
3 Zone -2 Drain Line Taping with Sprinkler Header 11-Sep-20 12-Sep-20 • Completed
4 11-Sep-20 12-Sep-20 • Completed
Zone -2&4 Below Mezzanine Header Connection
5 Bus Parking Hydrant Post Modification • Completed
6 External Hydrant Close Loop Tapping 17-Oct-20 18-Oct-20 • Fabrication done
7 Back Loading Bay Valve Installation 11-Sep-20 12-Sep-20 • Completed
8 Zone 2&4 Flow Switch Installation 17-Oct-20 18-Oct-20
9 Zone -2&4 Above Mezzanine Header Connection 17-Oct-20 18-Oct-20
• Fabrication Completed
5
Progress Pictures - Above Mezzanine Sprinkler
` • Completed
17-Sep-20 22-Sep-20
Internal Hydrant Hose Box Fixing for Zone-3,4& Below Mezz
2 23-Sep-20 • Completed
15-Sep-20
Above Mezzanine 1 Layer Sprinkler
st
10 - Oct-20
3 25-Sep -20 • Header Erection Completed
19-Sep-20
Above Mezzanine Hydrant System with Accessories 25-Oct-20
4 • Waiting for the Additional balance Reflector
Beam Device Re – Commissioning – 4 Nos
9 FAPA Demo and Hand Over with Warehouse Team 19-Sep-20 19-Sep-20 • Completed
26-Sep-20 26-sep-20
10 System Identification (Painting/Sticker)
12-Oct -20 14- Oct -20
External Hydrant
Support Painted
10
Progress Pictures
11
Thank You