Project : DTA – EX – WAREHOUSE Date :

30-09-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building)
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s

1 Project manager Helper 2

2 Project In charge 1 Fitter 1


3 Execution Engineer Welder 1

4 Planning Engineer Painter


5 Billing In charge Electrician 2

6 Billing Engineer

7 Quality Engineer

8 Contracts

9 Admin

10 Store In charge

11 Purchase

12 Accounts

13 Safety Asst. 1

2
2
FAS & PA Facility AdditionalTeam Requirements
S.No Description Remarks
1 Zone wise PA drawings required 1-Oct -20 will be Submitted

2 Above mezzanine floor PA speaker to be provided - Additional requirement Will be Done Along Second Layer Work

3 Zone wise PA speaker count to be provided in drawing 1-Oct -20 will be Submitted

4 Rest rooms to be provided with Sounders. - additional requirement. Need Confirmation Additional Qty

5 Transformer & HT panel rooms to be provided with MCP & Sounders - Need Confirmation Additional Qty
Additional requirement
6 FAS panel room detectors & Sounders - additional requirement Need Confirmation Additional Qty

7 Repeater panel location to be confirmed by Flex Location Need to Confirm for Cable
Laying
8 1-Oct -20 will be Submitted 1-Oct -20 will be Submitted

9 Beam detector approach requested by Flex facility team

10 Location details to be provided by Flex.

11 Approaching cable to beam detectors be laid in cable tray

3
Ware House – Modification Work
Sl. No Activities Description Start Date End Date Current Status as on date
FPS

1 Old Ware Sprinkler House Raiser & Hydrant Modification • Completed


19-Sep-20 20-Sep-20
Work
2 Zone -2 Branch Pipe Vertical Pipe Modification 11-Sep-20 12-Sep-20 • Completed
3 Zone -2 Drain Line Taping with Sprinkler Header 11-Sep-20 12-Sep-20 • Completed
4 11-Sep-20 12-Sep-20 • Completed
Zone -2 Above Mezzanine Header Connection
5 Zone –3 Raiser Modification
6 Bus Parking Hydrant Post Modification • Completed
7 External Hydrant Close Loop Tapping 08-Sep-20 09-Sep-20 • Fabrication done waiting for the clearance
8 Back Loading Bay Valve Installation 11-Sep-20 12-Sep-20 • Completed
9

4
Pump Room Material Delivery Schedule
Sl. No Activities Description Start Date End Date Current Status as on date
Pump Room

1 24-Nov-20 30- Nov-20


Pump Delivery ( All Pumps)
2 15-Nov-20 25-Nov-20
FM Gate Valves , NRV, Strainer
3 15-Nov-20 20-Nov-20
Pipes
4 20-Nov -20 25-Nov-20
Measuring Instruments
5 25- Nov-20 30-Nov-20
Aluminum Cable From Fire Panel to Pump
6 15-Nov-20 20-Nov-20
Weldable Accessories
7 25-Nov -20 10-Dec-20
Installation Work
8 25-Nov-20 30-Nov-20
PRV , Flow Meter
9 30-Nov-20 05-Dec-20
Panel Delivery

5
Pending Works Over All FPS/FAPA

Sl. Activities Description Start Date End Date Current Status as on date
No
FPS

1 Internal Hydrant Hose Box Fixing for Zone-3,4& Below Mezz 17-Sep-20 22-Sep-20 • Completed
2 15-Sep-20 23-Sep-20 • Completed
Above Mezzanine 1st Layer Sprinkle
3 19-Sep-20 25-Sep -20 • Header Erection Completed
Above Mezzanine Hydrant System with Accessories
4 • Awaiting for the Additional balance Reflector
Beam Device Re – Commissioning – 4 Nos

5 • Drawing Not Yet Confirmed from Consultant Side


Canteen Sprinkler - Work
6 • Civil Work Not Yet Completed
External Hydrant Pipeline at Chemical Room
7 Above Mezzanine 1st Layer Sprinkle • Completed

8 Above Mezzanine Second Layer Sprinkler Erection Work 05-Oct -20 21- Oct-20

9 FAPA Demo and Hand Over with Ware House Team 19-Sep-20 19-Sep-20 • Completed
26-Sep-20 26-sep-20
10 FPS Internal Demo and Hand Over With Ware House Team 03- Oct -20 03-Oct -20
11 External Hydrant Handing Over

6
Progress Pictures - Above Mezzanine Sprinkler

Zone -2

7
Progress Pictures - Above Mezzanine Sprinkler

Zone -4

8
Ware House – Internal FA & PA
Progress till Date

Sl. Description Planned Achieved Remarks


No
1 Cabling Laying 1to 14 Bay 1 to 14Bay 1 to 14 Bay Completed

2 1 to 14 Bay Device & Speaker Fixing 1 to 14 Bay 1 to 14 Bay Completed

3
1 to 14 Bay 1 to 14 Bay Completed
1 to 14Bay Beam Device Fixing

Full Area Completed Completed


Below Mezzanine Cable Laying
4

5 Below Mezzanine Device & Speaker Fixing with Cabling Cable & Device Fixing Cable Completed Completed
6 Above Mezzanine Cable Laying - -
7 Above Mezzanine Device & Speaker Fixing - -
8 Ancillary Building Cable Laying Canteen & 3rd Set Toilet Canteen & 3rd Set Toilet Completed
9 Ancillary Building Device & Speaker Fixing Canteen & 3rd Set Toilet Completed
10 Beam Device Re - Alignment 15 7 Nos Completed 5Nos Balance

9
Progress Pictures – Beam Device

Previous 4 Reflector Not


Able to Receive the Light
Rays to Receiver End @
98Mtrs Range

Now 9 Reflector able to


Receive the Light Rays to
Receiver End – Now
Working in 98 Mtrs Range
10
Ware House – Ancillary Building
Progress till Date

Sl. Description Planned Achieved Remarks


No
1 Chemical Building Wrapping Pipe Ready Awaiting for Construction
250MM Pipe Wrapping
Completion
2 Chemical Building Support Fabrication Completed Awaiting for Construction
Fabrication & Fixing of Support
Completion
3 Erection Above Ground Pipe Chemical Building
4 EMG -3 Wrapping Pipe Ready – 6Mtrs Awaiting for Construction
Erection Under Ground Pipe
Completion
5 Pond Side Yet to fabricate Awaiting for Construction
Hydrant post Pipe Erection Completion

6 Painting Activities Full Yard Hydrant 1week Before Handing Over

11
Thank You