Project : DTA – EX – WAREHOUSE Date :

21-10-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building)
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s

1 Project manager Helper 2

2 Project In charge 1 Fitter 1


Execution Engineer 1
3 Welder
4 Planning Engineer Painter 1

5 Billing In charge Electrician 1

6 Billing Engineer

7 Quality Engineer

8 Contracts

9 Admin

10 Store In charge

11 Purchase

12 Accounts

13 Safety Asst.

2
2
FAS & PA Facility AdditionalTeam Requirements
S.No Description Remarks
1 Zone wise PA drawings required As build Inputs Taken Soft Copy Shared

2 Above mezzanine floor AHU Room PA speaker to be provided - Additional Will be Done Along Second Layer Work
requirement
3 Zone wise PA speaker count to be provided in drawing As build Inputs Taken Soft Copy Shared
hard copy submitted

4 Rest rooms to be provided with Sounders. - additional requirement. Material Ordered will be Delivered in
22ndOctober
5 Transformer & HT panel rooms to be provided with MCP & Sounders - Material Ordered will be Delivered in
Additional requirement 22ndOctober
6 FAS panel room detectors & Sounders - additional requirement -

7 Repeater panel location to be confirmed by Flex Confirmed Cabling will be Started &
Finish it on 31-Oct -20
8 Beam detector approach requested by Flex facility team -

9 Approaching cable to beam detectors be laid in cable tray -

3
Pump Room Material Delivery Schedule
Sl. No Activities Description Start Date End Date Current Status as on date
Pump Room

1 24-Nov-20 30- Nov-20 • In Factory End


Pump Delivery ( All Pumps)
2 • Delivered
15-Nov-20 25-Nov-20
FM Gate Valves , NRV, Strainer
3 • Ready for delivery
15-Nov-20 20-Nov-20
Pipes
4 • Ready for delivery
20-Nov -20 25-Nov-20
Measuring Instruments
5 • Ready for delivery
25- Nov-20 30-Nov-20
Aluminum Cable From Fire Panel to Pump
6 • Ready for delivery
15-Nov-20 20-Nov-20
Weldable Accessories
7 25-Nov -20 10-Dec-20
Installation Work
8 • Ready for delivery
25-Nov-20 30-Nov-20
PRV , Flow Meter
9 • Place the PO Today
28-Oct -20 02-Nov-20
Panel Delivery

4
Ware House – Shutdown Work Work & Balance Work
Activities Description Start Date End Date Current Status as on date
Shutdown Work
1 Old Ware Sprinkler House Raiser & Hydrant Modification 19-Sep-20 20-Sep-20 • Completed
Work
2 Zone -2 Branch Pipe Vertical Pipe Modification 11-Sep-20 12-Sep-20 • Completed
3 Zone -2 Drain Line Taping with Sprinkler Header 11-Sep-20 12-Sep-20 • Completed
4 11-Sep-20 12-Sep-20 • Completed
Zone -2&4 Below Mezzanine Header Connection
5 Bus Parking Hydrant Post Modification • Completed
6 17-Oct-20 18-Oct-20 • Fabrication done
External Hydrant Close Loop Tapping 24-Oct-20 25-0ct -20
7 Back Loading Bay Valve Installation 11-Sep-20 12-Sep-20 • Completed
8 17-Oct-20 18-Oct-20
Zone 2&4 Flow Switch Installation 24-Oct-20 25-0ct -20
9 Zone -2&4 Above Mezzanine Header Connection 17-Oct-20 18-Oct-20 • Fabrication Completed
24-Oct-20 25-0ct -20
10 17-Oct-20 18-Oct-20 • Installed & Completed
Above Mezzanine BF Valve Installation for Isolation 24-Oct-20 25-0ct -20
11 17-Oct-20 18-Oct-20 • Fabrication Completed Tapping Balance
Water Monitor & Fire Brigade Installation 24-Oct-20 25-0ct -20

5
Progress Pictures - Above Mezzanine Sprinkler

Above Mezzanine Below to Above Internal


Sprinkler Header Hydrant Tapping
Tapping Pipe

1st & 2nd Layer 150mm


Isolation Valve
6
Progress Pictures - Above Mezzanine

External Hydrant Final Painting Completed


till UPS Room include support Painting
Further area Wall Painting not completed

4 Way Fire Brigade


7
Fabrication
Pending Works Over All FPS/FAPA
Sl. Activities Description Start Date End Date Current Status as on date
No

` • Completed
17-Sep-20 22-Sep-20
Internal Hydrant Hose Box Fixing for Zone-3,4& Below Mezz
2 23-Sep-20 • Completed
15-Sep-20
Above Mezzanine 1 Layer Sprinkler
st
10 - Oct-20
3 25-Sep -20 • Header Erection Completed
19-Sep-20
Above Mezzanine Hydrant System with Accessories 25-Oct-20
4 • Waiting for the Additional balance Reflector
Beam Device Re – Commissioning – 4 Nos

5 Canteen Sprinkler - Work • Header Work Stared


6 External Hydrant Pipeline at Chemical Room • Completed
7 Above Mezzanine 1st Layer Sprinkle • Completed

8 • Pipe Shifting completed & Erection


Above Mezzanine Second Layer Sprinkler Erection Work 20-Oct -20 31-Oct-20 started

9 FAPA Demo and Hand Over with Warehouse Team 19-Sep-20 19-Sep-20 • Completed
26-Sep-20 26-sep-20
10 System Identification (Painting/Sticker)
12-Oct -20 14- Oct -20

11 Hydrant hose box – 13 Nos 12-Oct-20 16-Oct-20 • Completed


12 12-Oct-20 16-Oct-20 • 1 Nos Completed
250NB Gate Valve – 2 Nos fixing
8
13 • Till UPS Room Completed Further Wall
12-Oct -20 17-Oct -20
Painting not Finished
Progress Pictures

Above Mezzanine 2nd Layer Sprinkler


Fabrication Work Pipe Shifted to
location

Above Mezzanine 2 nd Layer Sprinkler


1st Layer Red Paint applied

Above Mezzanine 2 nd Layer Sprinkler


9
Pipe Erection
Progress Pictures

Above Mezzanine 2nd Layer Sprinkler


Fabrication Work Priming Work
Above Mezzanine 2nd Layer Sprinkler
Fabrication Work Pipe Shifted to
location
10
Progress Pictures

Canteen Sprinkler Tapping Connection from


above Mezzanine

External Hydrant
Support Painted
11
Progress Pictures

Wall Painting Not yet


Completed

12
Thank You

13