Professional Documents
Culture Documents
Fps & Fapa - 3rd August
Fps & Fapa - 3rd August
Fps & Fapa - 3rd August
03-08-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building )
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s
6 Billing Engineer
7 Quality Engineer
8 Contracts
9 Admin
10 Store In charge
11 Purchase
12 Accounts
13 Safety Asst. 1
2
2
SITE TOOL BOX TALK (TBT) REPORT & PICTURES
3
Ware House – Internal Sprinkler Below Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
Electrical/FPS/HVAC Works
4
Ware House – Below Mezzanine
Progress till Date
5
Progress Pictures – Below Mezzanine Sprinkler
6
Progress Pictures - Below Mezzanine Sprinkler
7
Ware House – Internal Sprinkler Above Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
8
Ware House – Internal
Progress till Date
2
Zone 4 , Branch 3, 48mtrs Branch 3 ,48mtrs erection Branch 4 , 48mtrs planned
Support fabrication & Fixing planned for erection completed for tomorrow erection.
3 Header erection
Zone -4 prefabrication Zone -4 prefabrication Achieved
192mtrs planned 192mtrs planned
4 Branch Fabrication
9
Progress Pictures – Above Mezzanine
10
Progress Pictures – Above Mezzanine
11
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FAPA
1 Till 10th Bay Beam, FA&PA Completed
14-Jul-20 05-Aug-20
Erection Activities
2 Pre Commissioning 06-Aug-20 08-Aug-20 Zone -1 and 1st Set Toilet 1 Completed
3 Fire Logic testing 08-Aug-20 09-Aug-20
4 Testing 08-Aug-20 09-Aug-20
5 Snag Work
6 Measurement 10-Aug -20 11-Aug-20
7 As Build 10-Aug -20 11-Aug-20
8 Handing Over Draft Copy Submission 10-Aug -20 11-Aug-20
9 Handing Over hot Copy Submission 10-Aug -20 11-Aug-20
10 Completion Certificate
12
Progress Pictures – FA & PA Inside Rack Area
13
Progress Pictures – FA &PA
14
Progress Pictures – Auxillary Building FA & PA
15
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
16
Ware House – Ancillary Building
Progress till Date
3
Erection Above Ground Pipe
17
Progress Pictures – Bus Parking Side Gate Valve Erection
18
Handing Over Documents Submission Status
Sl. Description Submission Date of Submission Remarks
No Status
1 CONTRACT SPECIFICATIONS/PO COPY yes
Yes
2 WORK COMPLETION CERTIFICATE
5 OPERATIONAL MANUALS / DATASHEETS / CATALOGS OF ALL SUPPLIED AND INSTALLED ITEMS YES
20