Fps & Fapa - 10th Oct
Fps & Fapa - 10th Oct
30-09-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building)
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s
6 Billing Engineer
7 Quality Engineer
8 Contracts
9 Admin
10 Store In charge
11 Purchase
12 Accounts
13 Safety Asst. 1
2
2
FAS & PA Facility AdditionalTeam Requirements
S.No Description Remarks
1 Zone wise PA drawings required 1-Oct -20 will be Submitted
2 Above mezzanine floor PA speaker to be provided - Additional requirement Will be Done Along Second Layer Work
3 Zone wise PA speaker count to be provided in drawing 1-Oct -20 will be Submitted
4 Rest rooms to be provided with Sounders. - additional requirement. Need Confirmation Additional Qty
5 Transformer & HT panel rooms to be provided with MCP & Sounders - Need Confirmation Additional Qty
Additional requirement
6 FAS panel room detectors & Sounders - additional requirement Need Confirmation Additional Qty
7 Repeater panel location to be confirmed by Flex Location Need to Confirm for Cable
Laying
8 1-Oct -20 will be Submitted 1-Oct -20 will be Submitted
3
Ware House – Modification Work
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
4
Pump Room Material Delivery Schedule
Sl. No Activities Description Start Date End Date Current Status as on date
Pump Room
5
Pending Works Over All FPS/FAPA
Sl. Activities Description Start Date End Date Current Status as on date
No
FPS
1 Internal Hydrant Hose Box Fixing for Zone-3,4& Below Mezz 17-Sep-20 22-Sep-20 • Completed
2 15-Sep-20 23-Sep-20 • Completed
Above Mezzanine 1st Layer Sprinkle
3 19-Sep-20 25-Sep -20 • Header Erection Completed
Above Mezzanine Hydrant System with Accessories
4 • Awaiting for the Additional balance Reflector
Beam Device Re – Commissioning – 4 Nos
8 Above Mezzanine Second Layer Sprinkler Erection Work 05-Oct -20 21- Oct-20
9 FAPA Demo and Hand Over with Ware House Team 19-Sep-20 19-Sep-20 • Completed
26-Sep-20 26-sep-20
10 FPS Internal Demo and Hand Over With Ware House Team 03- Oct -20 03-Oct -20
11 External Hydrant Handing Over
6
Progress Pictures - Above Mezzanine Sprinkler
Zone -2
7
Progress Pictures - Above Mezzanine Sprinkler
Zone -4
8
Ware House – Internal FA & PA
Progress till Date
3
1 to 14 Bay 1 to 14 Bay Completed
1 to 14Bay Beam Device Fixing
5 Below Mezzanine Device & Speaker Fixing with Cabling Cable & Device Fixing Cable Completed Completed
6 Above Mezzanine Cable Laying - -
7 Above Mezzanine Device & Speaker Fixing - -
8 Ancillary Building Cable Laying Canteen & 3rd Set Toilet Canteen & 3rd Set Toilet Completed
9 Ancillary Building Device & Speaker Fixing Canteen & 3rd Set Toilet Completed
10 Beam Device Re - Alignment 15 7 Nos Completed 5Nos Balance
9
Progress Pictures – Beam Device
11
Thank You