Professional Documents
Culture Documents
Fps & Fapa 5th August
Fps & Fapa 5th August
05-08-2020
Subject : Site Progress Report ( Internal, External, Ancillary Building )
Vendor : Powerconz
Service
1 : Fire Fighting & FAPA System
Resource Sheet – Manpower
Contractor Staff Contractor Labour
Sr.No Manpower No.s Sr.No Manpower Area No.s
6 Billing Engineer
7 Quality Engineer
8 Contracts
9 Admin
10 Store In charge
11 Purchase
12 Accounts
13 Safety Asst. 1
2
2
SITE TOOL BOX TALK (TBT) REPORT & PICTURES
3
SITE TOOL BOX TALK (TBT) REPORT & PICTURES
4
Ware House – Internal Sprinkler Below Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
Electrical/FPS/HVAC Works
5
Ware House – Below Mezzanine
Progress till Date
3rd Progress
7
Progress Pictures - Below Mezzanine Sprinkler
4th
Progress
8
Progress Pictures - Below Mezzanine Sprinkler
4th
Progress
9
Ware House – Internal Sprinkler Above Mezzanine
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
10
Ware House – Internal
Progress till Date
2
Zone 4 , Branch 3, 48mtrs Branch 3 ,48mtrs erection Branch 4 , 48mtrs planned
Support fabrication & Fixing planned for erection completed for tomorrow erection.
3 Header erection
Zone -4 prefabrication Zone -4 prefabrication Achieved
192mtrs planned 192mtrs planned
4 Branch Fabrication
11
Progress Pictures – Above Mezzanine
12
Progress Pictures – Above Mezzanine
13
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FAPA
1 • Till 13th Bay Beam Device Completed
• PA & FAS Till 13th Bay Completed With Device
• Ancillary Building 1st,2nd Set Toilet with
14-Jul-20 05-Aug-20 Cabling and Device & Canteen Cabling Done
Erection Activities
2 Pre Commissioning 06-Aug-20 08-Aug-20 Zone -1 and 1st & 2ndSet Toilet 1 Completed
3 Fire Logic testing 08-Aug-20 09-Aug-20
4 Testing 08-Aug-20 09-Aug-20
5 Snag Work
6 Measurement 10-Aug -20 11-Aug-20
7 As Build 10-Aug -20 11-Aug-20
8 Handing Over Draft Copy Submission 10-Aug -20 11-Aug-20
9 Handing Over hot Copy Submission 10-Aug -20 11-Aug-20
10 Completion Certificate
Activities Planned for 28.07.2020
14
Progress Pictures – FA & PA Inside Rack Area
15
Progress Pictures – FA &PA
16
Ware House – Ancillary Building
Sl. No Activities Description Start Date End Date Current Status as on date
FPS
17
Ware House – Ancillary Building
Progress till Date
3 Yet to plan
Erection Above Ground Pipe
18
Progress Pictures – Ancillary Building
19
Progress Pictures – Ancillary Building
20
Quality Observation / Compliance Pictures
21
Quality Observation / Compliance Pictures
22
Quality Observation / Compliance Pictures
23
Handing Over Documents Submission Status
Sl. Description Submission Date of Submission Remarks
No Status
1 CONTRACT SPECIFICATIONS/PO COPY yes
Yes
2 WORK COMPLETION CERTIFICATE
5 OPERATIONAL MANUALS / DATASHEETS / CATALOGS OF ALL SUPPLIED AND INSTALLED ITEMS YES
25