Professional Documents
Culture Documents
SEE Presetation 2024[1]
SEE Presetation 2024[1]
Analysis (EVA)
A Comprehensive Guide to Project
Performance Measurement
Group Members
03 Jawad Ahmed
Fa21-Bse-068
04 Salah – ud -din
Fa21-Bse-075
Introduction to EVA
Definition:
Clarity:
EVA offers a clear and comprehensive view of project health by integrating scope, schedule, and
cost metrics into a single, unified system.
Decision Making:
By providing precise metrics on cost and schedule performance, EVA aids in making informed
decisions, optimizing resource allocation, and guiding project direction to meet objectives.
Early Warning:
EVA identifies variances from the project baseline early in the project lifecycle, allowing project
managers to take corrective actions promptly to mitigate risks and avoid potential issues.
Efficiency:
The technique improves cost control and schedule management by highlighting areas of
inefficiency and enabling project managers to implement strategies to improve performance.
Predictability:
EVA enhances the ability to forecast future project performance and outcomes by analysing
current trends and variances, thus helping in setting realistic expectations and achieving project
goals.
Key Benefits of Using EVA
Enhanced Tracking and Improved Schedule
Reporting Control
Objective Performance
Measurement
Informed Decision-
Making Better Cost Management
Key Components of EVA
The estimated cost of work The estimated cost of the actual The actual cost incurred for the
scheduled to be completed by a work completed by a specific work performed by a specific
specific date, representing the date, reflecting the value of date, showing the real
budgeted amount for the work performed if it is done expenditure spent on
planned work in the project within the budget. completing the work.
schedule.
introduction to
EVA Metrics
and Formulas
Introduction to EVA Metrics and Formulas :
Interpretation:
Question: What is the Schedule Variance (SV)?
PositiveSV
Solution: SV=indicates
$30,000 -the project
$35,000 is ahead(behind
= -$5,000 of schedule.
schedule).
Negative SV indicates the project is behind schedule
Performance Index (CPI) :
Definition: Measures the cost efficiency of budgeted
resources.
Formula: CPI = EV /Example
AC
Question
Explanation:
Scenario: A project has an Earned Value (EV) of $40,000 and an Actual
EV (Earned Value): The value of work performed.
Cost (AC) of $50,000.
AC (Actual Cost): The actual cost incurred for the work
performed.
Question: What is the Cost Performance Index (CPI)?
Solution: CPI = $40,000 / $50,000 = 0.8 (over budget)
Interpretation:
CPI > 1 indicates cost efficiency (under budget).
CPI < 1 indicates cost inefficiency (over budget)
Performance Index (SPI) :
Definition: Measures the schedule efficiency of time used.
Formula: SPI = EV /Example
PV Question
Explanation:
Scenario: A project
EV (Earned has The
Value): an Earned
value ofValue
work(EV) of $60,000
actually and a
performed.
Planned Value (PV)
PV (Planned of $55,000.
Value): The value of work planned to be performed.
Summary:
EVA metrics provide crucial insights into project performance and
progress.
Key formulas include CV, SV, CPI, and SPI.
Importance:
Helps in identifying variances in budget and schedule.
Facilitates informed decision-making to keep the project on track.
Enables better resource management and project control.
Estimate at Completion (EAC):
Estimate at Completion (EAC) is used to forecast the total cost of the project at
completion, based on current performance. There are several formulas for EAC, each
appropriate for different scenarios:
Standard EAC Calculation:
Example:
The CPI of 0.8 indicates that for every dollar spent, only $0.80 worth of work is being completed. This is
below the expected performance (a CPI of 1 would mean perfect performance).
The EAC of $125,000 means that if the project continues to perform at the current rate (CPI = 0.8), the total
cost at completion is projected to be $125,000, which is $25,000 over the original budget of $100,000.
Considering Schedule Performance:
● CPI of 0.8 indicates cost inefficiency, with only $0.80 worth of work completed for every dollar spent.
● SPI of 0.67 indicates schedule inefficiency, with the project progressing slower than planned.
● The EAC of $323,880.6 means that if the project continues to perform at the current cost and
schedule rates (CPI = 0.8 and SPI = 0.67), the total cost at completion is projected to be $323,880.6,
significantly over the original budget of $200,000.
When Future Work Will Be Performed at the
Budgeted Rate:
Example:
Assume a software development project has the
● EAC = AC + (BAC - EV) following baseline and performance data:
● Use this formula when you
believe future work will be
performed exactly as budgeted, Budget at Completion (BAC): $150,000
without considering current Earned Value (EV): $60,000
variances. Actual Cost (AC): $70,000
Interpretation:
● Early Warning System: These forecasting metrics help in identifying potential budget overruns and
schedule delays early in the project lifecycle, allowing for timely corrective actions.
● Informed Decision-Making: Project managers can make data-driven decisions regarding resource
allocation, scope adjustments, and performance improvements.