Introduction
Company name : JSW Project Topic : optimization of production cycle time for the product GI, GL, PPGI, PPGL. Under the guidance of Mr. Manoj kumar Jha.
About JSW
Founder 1952 1982 - vasind plant 1983 - Tarapur plant 1994 - Vijaynagar plant Investment Products
Production cycle
1 2 3 4 5 6
Sale order received from marketing dept. analysis of order order ganerated in oracle software order sign by production/QC dept. spec release ( technical specification)
H.R processing
G.L. finishing
dispatch
dispatch, 1 day G. L. finishing, 1 day H.R processing, 2 day spec release, 1 day
ANALYSIS OF DATA
PROCESS(including all) Sales Order Received Order Generated In Oracle Software Spec released. Slitting Pickling Rolling Galvanizing Colour Coating Dispatch STANDERD TIME -----1 day 1 day 1 day day day day day
ACTUAL DATE 25th April 2011 25th April 2011 26th April 2011 20th may 2011 21th may 2011 23rd may 2011 31st may 2011 31st may 2011 2nd june 2011
Recommendation.
Company can reduce scrap collecting time. i.e. 20-30 min by 5-10 min. By reducing fault in machineries by way of maintenance and repairs of machineries from time to time. The inventory should transfer to the next process without halt. The firm must use J-I-T inventory control tenchnique in production to minimize production process time. The technical specification(spec) should not be lated. Their must appropriate link exist between all department include marketing, PPC, costing.