S. No. 1 2 Site Intake Pump House. Description 6 Nos. Vertical Turbine Pumps of capacity 3000 m3/hr switch yard and MCC room.

Twin pipeline of 1422mm diameter of length 20.5 Raw Water Pipeline Total length 28.5 Km. km up to SH-63 crossing(Inclusive of 6.0 Km MCL area). Single pipeline of 1422mm diameter of 2km length up to Monnet Power Company Limited Gate. Single pipeline of 1200 mm diameter of 6km length up to plant reservoir.

Transmission Line.

15.2KM Tower line +15.3 KM Pole line after that 2 Km line from switch yard to Pump house to be laid. 5 Nos. of River crossing. 5 Nos. of road crossing: (03 Rural Roads and 02 State Highway - PWD Roads).

River and Road Crossing.

11.04.11

Civil @ Intake Pump House Major civil works at intake pump house are completed and the pending works are as follows:
S.No Work Description 1. 2. Area leveling & Approach roads. Quantity 450 Mtrs. Completion Remarks Date 25.10.2011 20.10.2011

Valve pits for DN 2000 3 Nos & DN 1400 valves. Final coat painting Click to house, inside pumpedit Master subtitle style doors, windows & EOT crane Plumbing and sanitary arrangement for staff quarters & MCC room. Drains, stone gabion, balance boundary wall. 3/5/12

3.

20.10.2011

4.

15.10.2011

5.

30.10.2011

Balance Mechanical work at Intake pump house


S.No Description 1 2 3. Pump motor erection & alignment Quantity Completion date Remarks 03 Nos. 20.10.2011 10.11.2011

Mechanical Erection @ Pump House

Stop Log Gate Alignment 09 Nos.

4.

Supporting structure for 80 MT 10.11.2011 Coarse, trash, stop log gates & hoists Click to edit Master subtitle style Erection of Hoisting 3 Nos 10.11.2011 arrangement for coarse, trash & stop log gates Erection of DN 800 & 2000 valves 19 Nos. 20.11.2011 15.11.2011 10.10.2011

4. 5.

Laying of DN 2000 main 90 Mtrs. line header 72 Mtrs.

6. 3/5/12 Laying of DN 1400 pipe

Pipe LineName StatusChainage Agency


0 15.2 Km Shivashakti =10.702 Km Elemech (P) Ltd. completed . R.S. Consultants. New Touch India. Sadhna & Usha Projects. Maa Transport 15.2 20.7 MCL Area. Km 20.7 28.2 Unitech Engg. Km =6.220 Km Pradhan completed. 0 6.7 km

Progress ( Sept-11)

Cumulative status

Trenching -140 m Trenching 5564 m Pipe Laying 103 m Pipe Laying 5094 m Trenching - 27 m Pipe Laying 66 m Trenching 3057 m Pipe Laying 3030 m Trenching 257 m Pipe Laying 225 m 2210 m completed. Trenching 315 m Pipe Laying 144 m 1.2 Km stretch cleared and demarcation started. Trenching - 33 m Pipe Laying 31 m Trenching 2181 m Pipe Laying 2158 m Trenching 60 m

6.7 8.76 km 12.4 - 14.1 km

8.76 10.19 km Left the job. 10.19 - 12.4 km Left the job. 6.7 9.64 Km 14.1 - 15.2 km 6.0 Km Trenching -50 m Pipe Laying 36 m

Single line 2.8 km : SH-63

work order for Trenching - 60 m balance work of Pipe Laying 60 m M/s Unitech to be issued. Single Line 2.4 km: SH-63 Trenching - 0 m Pipe Laying 0 m

Surya Engg. Sheetal Engg.

Trenching 1484 m Pipe Laying 1484 m Trenching 1832 m Pipe Laying 1832 m Trenching 638 m Pipe Laying 634 m

3/5/12

Rajesh Construction.

Single Line 1.9 km Trenching - 0 m (JSPL Gate to Pipe Laying 0 m Reservoir) 0.7 Km Trenching - 0 m Pipe Laying 0 m

33KV Transmission Line


S. No. Description Total Progress (SeptNos 11) Cumulative till date Remarks Transmission line ( 15.2 Km Tower+6.0 Km U/G Cable + 7.0 Km Pole) 15.2KM 33 KV Transmission Tower Line 1. 2. 3. Foundation Tower Erection Stringing 125 125 15.2 Km 06 05 94 77

6.0 KM 33 KV U/G cable 1.

Click U/ G Cable

to edit 6.0 KM Cable understyle Master subtitle


procurement & pre cast cable trench to be arranged.

7.0 Km 33 KV Pole Line 1. 3. Pole Erection Stringing 140 7.0 Km 20 0.4 Km 117 4.5 Km

3/5/12

Major Activities planned for Sep11


S.No. Major Activities 1. Motor erection and final alignment Fabrication of supporting structure for Trash screen, coarse screen, stop log & hoisting arrangement Supply of DN 2000 Pipe Completion of valve pits for DN 2000 & DN 1400 valves Laying of DN 1400 pipeline (Cross Country) Civil foundation for 33kv transmission tower line. Erection of towers for 33kv transmission tower line. Target 06 Nos Status Remarks

03 Nos 03 Nos erection in progress. 40 MT 74 Mtrs. Raft completed and side walls in progress. Rain fall & local issues 0.3 Km affected the progress. 6 Nos 5 Nos 20 Nos

2. 3. 4.

50 MT 90 Mtrs. 3 Nos.

1.5 Km

5. 6. 7.

10 Nos 10 Nos 15 Nos

Erection of Pole line 8. 3/5/12

Areas of concern
1.

2. 3.

4. 1. 2.

3. 4.

5.

6.

Permission for laying of pipeline & Transmission tower line in MCL land. Resolving ROU / ROW issues without hampering work. Laying of pipeline @ River / Nalla , Road, NTPC bridge Crossings. Laying of pipeline in Nisha Village. Hydro testing of pipeline. Pending electrical supplies by JWIL for intake pump house. Theft of transmission tower material after erection. Click to edit Master and stringing for transmission tower Fixing of conductors subtitle style line. Timely release of payments to contractors against RA bills. Resolving of all pending issues for smooth flow of work (Pipe storage yard lease, security payments, wrapping coating, pending dues in all villages with JWIL sub contractors).

3/5/12

Major Activities planned for Oct11


S.No. Major Activities 1. Target Status Remarks

Completion of entire balance civil work 30.10.2011 @ Intake. Balance 3 Nos of Motor erection & final alignment and discharge connection 25.10.2011 with DN 800 spools. 80 MT Supporting structure erection of 21.10.2011 Trash gate, coarse gate, stop log gate & mono rail Fabrication of DN 2000 Y- piece and Miter Bend and laying of pipeline (Intake) 20.10.2011

2.

3.

4. 5. 6. 7 7. 8.

Laying of DN 1400 pipeline (In-take)- 72 10.10.2011 Mtrs. Laying of DN 1400 Twin Pipeline (Cross Country) Laying of DN 1200 single Pipeline (Cross Country) Civil foundations for transmission tower line 2 Km 0.8 Km

10 Nos. 10 Nos.

3/5/12 Erection of transmission towers