Professional Documents
Culture Documents
Mumbai Monorail Project
Mumbai Monorail Project
CONTENTS
Back Ground and History Introduction to Monorail Piling Work Reinforcement and Preparation of BBS Work Methodology of Concrete Production, Transportation, Placing and Curing
Casting yard
Methodology of Structural roofing.
2
THE BACKGROUND
Considering the increase in population, increased travel demand and narrow road networks running through congested structures, there is a need of a system which will occupy less
HISTORY
Vilasrao Deshmukh, cleared the notification for construction of the first monorail system in India on August 13, 2008.
The two shortlisted consortia to build the line were Reliance Energy in association with Hitachi Monorail, and Larsen and Toubro with Scomi Rail of Malaysia.
On November 11, 2008, the winner was announced to be Larsen and Toubro along with Scomi, who received a INR 2460 crore contract to build and operate the monorail
4
INTRODUCTION
for
passenger or freight vehicles. Mostly elevated, monorails can also run at high curves and gradients or subway tunnels. This is first monorail project in
Mumbai , India.
5
ADVANTAGES
The primary advantage of monorails over conventional rail systems is that they require minimal space. They are quieter, as modern monorails use rubber wheels on a concrete track. Whether they are of the straddle-beam or suspended variety, the nature of their design does not allow derailment. As monorail is elevated, accidents with surface traffic are impossible Monorail does not obstruct much sunlight Minimum use of land and save cost Less disruptive to road traffic Pre casting allows more off-site construction Add aesthetics to the city due to greenery along the road and appearance
DISADVANTAGES OF MONORAILS
Monorails have constraint of load carrying capacity as compared to other transit systems because they employ rubber tires instead of steel.
Client: MMRDA PMC: Louis Berger Group Inc. Contractor: L&T Scomi Engineering. Consortium Turnkey Built and Contract 3 years- Operation and Maintenance Date of Commencement: 14th November, 2008 No of stations: 17 numbers Depot: 1 number Journey time: 37min No of cars: 4 Passenger carrying capacity: 568 per train Average speed: 31 kmph Max speed: 80 kmph
PILING WORK
Due to soft rock available at Bhakti Park between 12 to 20 m Pile is basically BORED CAST-IN-SITU PILES (Friction piles).
MATERIALS USED
a)
b) c)
HYDRAULIC RIG-180
11
PROCEDURE
1.
Firstly Surveyor with the help of Total Stations gives centre point with the help of Northing and Easting bearings as per
Drawing and then gives two reference points 500mm apart from
the edge.
2.
The impression of boring tool shall be made Drilling shall start immediately and bore shall reach the required depth as shown in the drawings
12
7) The Verticality of Drilling / bore shall be checked periodically with the help of SPIRIT LEVEL (vertical, horizontal, inclined 45 degree).
8) Sounding test is done to check the depth is as per drawing. 9) Prefabricated Reinforcement Cage
Concrete Cover blocks giving cover of 40mm to the reinforcement Helical Reinforcement of diameter 8mm. Main reinforcement of diameter 12mm,16mm,20mm and 25mm Master Ring of diameter 12mm Lifting Hook of diameter 16mm
14
SPECIAL CASE:
In case of collapsing cleaning is done with the help of Cleaning Bucket and LINER is taken out and welding is done (electric arc welding) up to soft level.
15
16
FIELD TESTS:
1) SLUMP TEST
18
12
12 12 16
1
8 8 2
1
1 1 1
1
8 8 2
Helix
Lap in helix Master ring Lifting hook
90.913
.480 1.264 .6
90.913
3.84 10.112 1.2
80.731
3.41 8.979 1.89
19
For plain or reinforcement cement concrete or pre-stressed concrete, the reinforcement shall be grade Fe500 HYSD bars.
Use of stirrups mainly of 8mm Spacer bars or Chairs at approx. 1m intervals shall separate layers
of the reinforcement .
20
Bars with cranks are provided in beams for overlapping and proper
cover.
21
22
Sand Blasting
Primer coating Seal coating
c)
23
TOLERANCES:
or 5mm
24
CONCRETE PRODUCTION
25
SWING STETTER
Transportation of concrete: The concrete shall be supplied in continuously agitating transit mixers. Placing of concrete: The placing shall not commence until the reinforcement is tied properly, insert plates placed, the formwork is to the lines, shapes, and dimensions given in the approved drawings.
Placing Tremie concrete
Pumped Concrete Crane Bucket or Manual
Slump(mm) 175+-25
100-150 100+-25
26
27
COMPACTION:
28
BLOCK WORK
Concrete Blocks: Precast solid cement concrete blocks should be from an approved source. Length tolerance = 5mm Width and Height tolerance = 3mm Density > 1800kg/m3 Compressive Strength > 5N/mm2 Water absorption < 10% by mass Cement: Ordinary Portland cement, 53 Grade Masonry Mortar: Grade of masonry mortar MM5 (1 Cement : 4 Sand)
29
Laying of Block work Block wall thickness: 200mm and 100mm as per architectural drawings. Size of block for all inner walls = 390 x190 x 90 mm Size of block for all outer walls = 390 x140 x 190 mm
30
PROPER RACKING
1) There should be proper hacking 2) There should be proper racking and proper horizontal and vertical leveling.
31
32
33
PLASTERING OF WALLS:
Equipments:
Scaffolding
Mixing tray
Float, Trowel Plumb bob, Leveling tube
Materials:
source.
Internal plaster thickness- 12-15mm External plaster thickness- 20mm in two coats
35
PLASTERING OF CEILING:
36
37
30-40mm
38
39
CPCC coated Fe 500 HYSD bars are used Bottom rebar tying Placing of sheathing for pre stressing cables
Use of steel wire of dia 1.5mm to tie bars with each other
41
ALIGNMENT OF SOFFIT
LIFTING OF CAGE
Use of TRUSS is to lift the cage One end of the Truss is attached with HOOKS which is further attached with cage and other end is attached with the GANTRY GIRDER Reinforcement cage which is initially straight is put on the soffit and with the help of two GANTRY GIRDERS Reinforcement is aligned according to soffit
43
End Shutter is of Steel and certain Provisions are there Provision for development bars
Use of SPRING
Sheathing is attached to the cone
Oiling of shuttering
45
47
TESTS PERFORMED
Temperature test Slum test Cube testing -12 cubes are casted and put it in water for
curing for 28days and are tested for7 days and 28 days
48
During concreting
After casting
49
CURING YARD
After 1 day shuttering is removed and trolley is moved to the Curing Yard for the curing purpose. MEMBRANE CURING
50
Finishing is done with (1/2 acrylic base amrocrate solution + 1/2 cement -opc53)
51
STRESSING YARD
A 12-16 gauge GI wire (High tensile steel strands) have large diameter coils, so that Tendon retain its physical properties.
52
53
The mix for grouting cables/ducts is OPC53 mixed with water to obtain water-cement ratio of not more than .45.
STACKING YARD
With the help of gantry girders having 75MT capacity beams lifted and stacked into the stacking yard
Beam shift Shift trolley along with soffit using gantry
55
56
57
Painting of Structural steel column will be done and thickness is measured by ALCOMETER
58
Erection
of Column
Arc welding
59
60
Thank you
61