Professional Documents
Culture Documents
IEC 62271 202 Standards en
IEC 62271 202 Standards en
Safety is a choice
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
> Introduction
UL
IEC
IEC
> Introduction
Introduction
IEC 62271-202 standard specifies the rated characteristics, the design and construction rules and the test methods applicable to prefabricated substations.
> Introduction
Introduction
These substations are located in places accessible to the general public. Consequently, safety of persons must be guaranteed Conformity to the IEC standard guarantees: Protection of the general public Protection of operators
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
Type-tested equipment
All substation components must conform to IEC standards and in particular:
Mechanical resistance of the enclosure Sound level Degree of protection Insulation level
MV
Biosco W
Biosco N
Biosco H
Biosco U
10
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
11
1. Dielectric tests 2. Temperature rise tests 3. Main circuit and earthing tests 4. Functional tests 5. Degree of protection verification tests 6. Mechanical tests 7. Arcing due to an internal fault tests
12
Dielectric tests
Aim of test To guarantee insulation of HV and LV interconnections
Our performance The HV and LV interconnections of the Biosco range are tested as per standards IEC 60694 and 60439 Example for 24 kV switchgear: Withstand to voltage of 50 kV at power frequency for 1 min Withstand to lightning impact voltage tests for a 1.2 s wave and a voltage of 125 kV
13
To determine the enclosure class To guarantee that none of the substation components will overshoot its standard-defined limits To guarantee temperature on the parts of the enclosure likely to be touched during operation To guarantee lifetime of insulating devices and thus safety of equipment during the period of operation
Our performance
The Biosco substation enclosures are class 10 as standard This performance can be adapted to your needs according to ambient temperatures, degrees of protection or transformer losses Numerical modelling and thermal simulations are performed.
14
Our performance
15
Functional tests
Aim of tests To guarantee that it is possible to carry out all the operations required for commissioning, operation and maintenance Our performance The Biosco substations undergo a series of verifications Switchgear operation Mechanical operation of substation doors Reading transformer temperatures and oil levels Monitoring voltage readings Installation of earthing devices Cable tests Replacement of fuses and monitoring of locking systems Operating the transformer on-load tap changer Cleaning the ventilation grids Monitoring the locking systems
16
Our performance The degree of protection of the Biosco substations is between IP23 and IP54 This performance can be adapted to your needs: stipulations of standards and climatic requirements.
17
Mechanical tests
Aim of test To guarantee withstand of roof in event of overload: people, snow, etc. To guarantee the resistance of substation to wind pressure and to mechanical impacts on walls, covers, doors, ventilation opening.
Our performance
Roof withstand greater than 250 daN/m IK10 (including doors and ventilation grids)
18
19
Aim of test
To ensure that the substation enclosure does not increase the transformer noise level.
Our performance
20
To satisfy emission requirements laid down by international standards To guarantee the proper operation of equipment in an environment comprising large electromagnetic disturbance sources
Our performance
HV and LV switchgear comply with the specifications of standards IEC 60694 and 60439-1. Electromagnetic fields are simulated.
21
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
22
A specification tool
Standard IEC 62271-202 tells users which information should be supplied for invitations to tender and orders.
Network specificities Nominal and highest voltages Frequencies Neutral earthing mode Operating conditions Minimum and maximum temperatures Altitudes
The specificities and electrical characteristics of prefabricated substations Voltage, power, frequency
23
A specification tool
The information required for specifications is summarised in table form. All the electrical utility has to do is complete this information.
24
Contents
Introduction Type-tested substations The type tests A specification tool Conclusion
25
Conclusion
Type-tested MV, LV equipment and transformer
A series of type tests to guarantee safety and reliability of the prefabricated substation throughout its life cycle.
Use of equipment conform to IEC standards Electromagnetic compatibility Functional tests Temperature class Non LV flammable materials Earthing circuit test
Mechanical resistance of the enclosure Sound level Insulation level MV Internal arcing withstand Oil retention
An MV/LV substation specification guide providing all characteristics and installation and operation conditions
26
27